TelePhone 0086 15311826613
WhatsApp

15011319916

微信二维码

Wechat QR code

Home News Mineral processing knowledge You should remember these 6 major installation points for mechanical agitation flotation machines!

You should remember these 6 major installation points for mechanical agitation flotation machines!

2021-08-04 Source: Xinhai(1332views)

Welcome to consult Xinhai - customized mineral processing plan

Xinhai can provide you with mineral processing tests, mineral processing process and mineral processing equipment selection, mineral processing plant scheme design and construction drawing design; provide mining mineral processing equipment; provide mineral processing plant construction and equipment installation as well as mine management and operation services.

添加微信:15311826613

15311826613

Click to add WeChat
WeChat ID has been copied, add friends, and get manufacturer quotations!

Mechanical agitation flotation machine is a very commonly used flotation equipment in mineral processing plants. In daily applications, whether the flotation machine can continue to operate normally and whether the sorting index can meet the standards depends largely on whether the installation and debugging are complete. The installation and debugging of the mechanical agitation flotation machine is a must before the entire plant is officially put into production. Everything you go through is very important. Below, this article shares with you the 8 major installation and debugging points of the mechanical agitation flotation machine to help you install the flotation machine correctly.

Mechanical agitation Installation and debugging of flotation machine

The mechanical agitation flotation machine mainly consists of a tank body, a stirring mechanism, a scraper mechanism, a liquid level control mechanism, and a gate mechanism. , ore-drawing mechanism, etc. During the installation and debugging process, the installation and debugging steps of each part are as follows:

1. Installation and debugging of the flotation machine tank

The installation of the mechanical agitation flotation machine tank must be ensured correctly. In the installation sequence, the head tank body should be installed first, then the middle tank body, and then the tail tank body. In addition, before installing the tank, the installation and debugging personnel need to use a level surveyor to measure the horizontal deviation of the foundation. After the tank is installed on the foundation, the overflow weirs on both sides of each tank should be at the same level. Use a level ruler to measure the horizontal deviation of the foundation in different tanks. Align the body and use pads of different thicknesses to keep the whole machine level and consistent in the length and width directions.

Stirred type Flotation machine tank installation

Generally, the total deviation in the length direction should not exceed 3-5mm, the feed inlet, tank body and tank body, tank body There should be no leakage at the connection part with the medium ore box, and then tighten the bolts of all parts of the body.

2. Installation and debugging of the flotation machine mixing mechanism

The following requirements must be followed when installing and debugging the mixing mechanism:

1. The hollow shaft and impeller should be installed Reliable, the horizontal plane of the impeller should be perpendicular to the hollow shaft, and cannot move up and down.

2. The impeller should be centered with the center hole of the false bottom, and the deviation should not be greater than 3mm.

3. The stator guide blades are aligned with the flow stabilizing plate on the false bottom and must not be staggered.

4. The radial and axial clearance between the impeller and the stator should be guaranteed to be between 7-9mm. During installation, any three points at equal distances from the outer diameter of the flotation machine impeller can be measured. Clearance, axial clearance is adjusted by adjusting pads.

Flotation machine impeller

5. The installation tightness of the transmission V-belt should be moderate. Before installing the V-belt, first install the large and small pulleys on the motor and mixing shaft appropriately, and then level the V-belt. Put the belt into the pulley groove, adjust the center distance, and tighten the V-belt. Turn the motor to continue adjusting the V-belt so that the loose edge is slightly bowed when driven with load.

6. Install the triangular pulley safety cover, and the safety cover legs should be inserted into the pipe base firmly.

7. Check the direction of motor rotation. The impeller rotates clockwise. The mixing mechanism should rotate flexibly and without jamming.

3. Installation and debugging of the flotation machine scraper mechanism

When installing the flotation machine scraper shaft, scraper frame, and scraper rubber, the scraper shaft should be able to rotate. And the gap between the scraper rubber plate and the overflow port should be consistent and should not be greater than 5mm. The scraper of the final slot should be staggered by 30° from the scraper of the previous slot.

Flotation machine stirring Mechanism installation

The centers of the scraper shafts are all on the same straight line, and the coaxiality deviation of two adjacent shafts is not greater than 0.8mm.

4. Installation of the liquid level control mechanism, gate mechanism and ore discharge mechanism of the flotation machine

When installing the fixed liquid level adjustment mechanism of the mechanical agitation flotation machine, the The mechanism can be raised and lowered flexibly under manual or automatic operation, and within the lifting range required by the design; the gate mechanism should ensure that the gate can be raised and lowered flexibly without leakage; the installation of the ore-drawing mechanism should ensure that the hand wheel rotates flexibly.

5. Lubrication and cleaning of the flotation machine

After the flotation machine is installed, various greases should be injected into each lubrication point according to the design requirements, and any grease that falls into the tank during the installation process should be cleaned. Bolts, cotton and other foreign objects in the machine.

Flotation machine cleaning

6. Inspection and trial operation of the flotation machine

Fill the overflow port with water, and without starting the stirring mechanism, Check the installation level of the tank and whether there is any leakage. After the inspection is normal, start the motor and run it without load for 8 hours. Check the current of the motor and the heating of each part. If there is no abnormality, it can be run with added materials.

The above are the 6 major installation points of the mechanical agitation flotation machine. Do you remember it?

24-hour service hotline 0086 15311826613

Message


WhatsApp

WhatsApp

ConsultConsult messageMessage E-mail

Email

xhshicuiping@dingtalk.com